How to Read a Roof Quote: The 6 Lines Every Bid Should Show

By John Dudley, 30-year general contractor and co-host of Around the House
A homeowner wrote this fall about four roof quotes. One roofer came in at $8,000. The other three came in between $13,000 and $15,000.
Your first thought is the same as theirs: either the cheap guy is too good to be true, or the other three are padding it.
Neither one, necessarily. The $8,000 quote was a layover. The other three were tear-offs.
A layover means new shingles go on right over the old ones. A tear-off means the old roof comes off down to the deck, somebody looks at the wood underneath, and the new roof goes on from there. The layover skips the tear-off labor, the dumpster and the dump fees, so of course the number comes down. It also means nobody sees the decking before it gets covered again, and whoever does the next roof has two layers to take off instead of one. Whether a second layer is even allowed depends on your town’s code and on what’s already up there.
Same roof. Different job.
That’s the whole problem in one sentence. Put a layover and a tear-off on two quotes that each say “Replace roof,” and they look like the same job at two prices. A roof quote that’s one line long isn’t a price. It’s a guess with a dollar sign on it, and you can’t compare a guess to anything.
Homeowners say the same things over and over: one roofer was on the property twenty minutes, another priced it off a satellite photo, and neither one explained what he found. Another homeowner found out something they assumed was included wasn’t in the quote at all. Another got a quote where the materials line was just left blank.
None of that means the roofer is crooked. It means you’re missing the lines that tell you what you’re buying.
Here are the six I’d want to see on any roof quote before I signed it. Lay your quotes side by side and go line by line.
1. Tear-off and disposal
What it should say: how many layers of old roofing come off, and that hauling it away (the dumpster or trailer, the dump fees) is included.
Why it moves the price: a second layer of shingles under the first is real labor and real weight going to the dump. If one roofer priced one layer and another priced two, they aren’t quoting the same job. If one quote takes nothing off at all, that’s a layover, and it isn’t the same job as the other three. And a quote that never mentions disposal leaves you asking who’s paying for the dumpster.
Ask: “How many layers are you taking off, and is the dump fee in this number?”
2. Decking repair allowance
What it should say: what happens if the plywood or boards under the shingles are rotten. The good quotes put a price on it per sheet, and say how many sheets are already included, if any.
Why it moves the price: nobody can see the decking until the old roof is off. So this is where surprise bills come from. A low quote with no decking line can be the most expensive quote of the three once the roof is open.
Ask: “If you find bad decking, what do you charge per sheet, and how many sheets are already in this price?”
3. Underlayment and ice-and-water shield
What it should say: what goes down between the deck and the shingles (synthetic or felt), and where the ice-and-water membrane goes: the eaves, the valleys, around chimneys and skylights.
Why it moves the price: this layer is what keeps water out when a shingle lifts or wind drives rain sideways. In cold country, a lot of local codes call for ice-and-water shield at the eaves. Two quotes can use the same shingle and be very different roofs underneath.
Ask: “What underlayment are you using, and where does the ice-and-water go?”
4. The shingle, by name and grade
What it should say: the manufacturer, the product line, the color, and the grade (three-tab or architectural, for example). Not just “shingles.”
Why it moves the price: shingle lines run from basic to premium, and the warranty that comes with them changes too. If one quote names the product and another says “shingles,” you can’t tell whether you’re comparing a Chevy to a Chevy.
Ask: “Which shingle exactly? Can you write the product name on the quote?”
5. Flashing, vents and everything that goes through the roof
What it should say: drip edge, step flashing along walls, chimney flashing, pipe boots, and vents. For each one: new, or reused?
Why it moves the price: most leaks don’t start in the middle of the roof. They start where the roof meets something: a wall, a chimney, a pipe, a vent. Reusing old flashing saves the roofer time and money on the bid. It can cost you later.
Ask: “Are you replacing the flashing and pipe boots, or reusing what’s there? What about the vents?”
6. Permit and cleanup
What it should say: who pulls the permit (if your town requires one) and that the permit fee is in the price. Then cleanup: tarps over the landscaping, a magnet sweep for nails in the yard and driveway, and the site left clean.
Why it moves the price: permits cost money and take time, and some quotes quietly leave them out. Code items can also show up after you’ve agreed to a number. Cleanup sounds small until there’s a roofing nail in your tire.
Ask: “Who pulls the permit, is the fee included, and what does cleanup look like on the last day?”
Now compare them
Put the quotes next to each other and check off the six lines. What usually happens:
- The high quote names everything. Maybe it’s high, maybe it’s just complete.
- The middle quote names some of it.
- The low quote names almost none of it.
Now call the low guy and ask him the six questions. If his answers bring his number up to the others, you just found out what the spread was. If he holds his number and writes all six lines down, maybe he’s your roofer. And if line 1 says “layover,” you’re not choosing between a cheap roofer and an expensive one. You’re choosing between two different jobs.
And if he won’t itemize, ask why.
A roofer who knows his costs can tell you what’s in the price. It’s not a trade secret. It’s the job.
If you’re the contractor reading this
Your customer is going to read something like this. Then she’s going to ask you what’s in your number.
If you priced the tear-off and the other guy priced a layover, nothing tells her so but your paper. Write the tear-off, the dump and the decking down, line by line, and she can see the difference herself. You don’t have to knock the other guy. The lines do it.
That’s the question InstaBid is built to answer. It itemizes every estimate to the stick, with a full scope of work, under your name. It prices the job from your real cost, and your markup goes on top where you set it. Eleven trades, roofing included. Under two minutes from describing the job to the finished estimate.
The itemized contractor wins that conversation by default.
More straight talk on hiring a contractor and fixing your house: Around the House.
Deja de perder trabajos por presupuestos lentos.
Tu cliente pregunta, InstaBid arma el presupuesto, tú apruebas con un toque. Pruébalo: 10 días gratis, sin tarjeta de crédito.
Empieza gratis →